Have you ever imagined hospital shutdown in the middle of summer? It is possible if one of the critical equipment is not functioning due to various reasons. Typically those issues are associated with waste of energy. As mentioned last time, almost all the heat removed from the hospital is rejected to atmosphere via cooling towers. If the cooling towers are malfunctioning, the whole cooling system will be in trouble and shutting down the hospital is inevitable.
To get the best performance from the cooling towers, regular inspection and maintenance are highly desired. The team noticed the performance of 2 out of 3 cooling towers was deteriorating last summer: return water temperature from the cooling towers was much higher than it should be. Actually the temperature is high enough for someone to take a shower inside the cooling towers. If this was not corrected, not only electricity is wasted but also chiller surge or chiller damage will occur. One of the chiller manufacturers, Carrier explained chiller surge quite well in plain language as following:
“When the lift (the pressure difference between the condenser and the cooler) imposed on a centrifugal compressor’s impeller is greater than the impeller can maintain, the refrigerant flows from the condenser back through the impeller to the cooler. The amps and the condenser pressure drop while the cooler pressure rises and the noise level changes. As the pressure difference decreases, it reaches a point where the impeller starts lifting again. If the cause of the high lift remains uncorrected, the surge continues in a cyclic pattern that repeats at a frequency dependent on the lift but usually several times per minute.”
Extended chiller surge can cause damage to compressor seal, bearing, impeller, shaft and driver or even catastrophic failure and all those start from the cooling towers. The cooling tower supplier was contacted to inspect the cooling towers and identify the root causes. They found that the original spray nozzles are too small and they got clogged easily. There were also scale buildup on some of the fill media and damage to the fill media due to water erosion.
Figure 1 Scale, rust and debris removed from one of the distribution pipes during the tower repair project.
Figure 2 Severe scale buildup on fill media
Based on the inspection report and our own observation, we created a scope of work to repair the cooling towers. New nozzles with much larger opening and new fill media would be installed. One of the measures we added is from our maintenance/operating engineer Betrework Wondmeneh (his photo can be found here). He noticed some of the broken fill media and splashing baffle pieces ended up inside the chiller condenser tubes. The strainers on cooling tower sumps and condenser water pumps were not working properly. He replaced pump strainers but for the sump strainers there is no ready solution since the existing design of fasteners holding the strainers appear to be weak and there are always water turbulence in that area. Drilling new holes on tower body for strainer installation may cause water leakage. After some trial he got this great idea of installing steel rods on top of the strainers and proved it works well. A round rod will not pick up the force from water turbulence and will hold down the strainer in the right location.
Figure 3 New spray nozzles with larger opening.
Figure 4 New stainless steel rods to hold down the sump strainer.
Fortunately the Energy & Environment team received approval of more retro-commissioning funds because of great success in the past. A construction team was assembled and the target is to complete the full scope of work before the cooling season started. We started from the cooling tower that was in worst shape. After it was opened up and some of the damaged fill media on top was replaced, it was noticed that there was heavy scale buildup on the rest of fill medias. A water treatment company was called in to do chemical cleaning. After two tries, the results were still not satisfactory. To make it right, all the fill medias on this cooling tower were replaced. This was quite some change on scope of work and finance, procurement and even higher management were involved to approve the change within a couple of days so that we can complete the project by the deadline. The cooling tower repair company, chemical cleaning company and UHN worked seamlessly as one team.
Eventually the project was done before the cooling season started and all the cooling towers have been performing well. Possibility of chiller surge was eliminated and costly hospital shutdown was avoided. Electricity demand profile shows that under similar weather conditions (84°F outside), we saved about 633 kW when compared with that from about one year ago. It is estimated that total of $31,600 will be saved per year – another successful energy retrofit project.
Figure 5 Electricity demand profile shows savings of 633 kW.
In the end of the day, Betrework can concentrate on something else important: “Since the completion of the repair work on the 3 cooling towers, the chillers are working smoothly without surge. The water coming from towers is cool between 78°F and 86°F in summer and I am sure there is no more broken fill media pieces going in the system because of the rods and new pump strainers. I’m closing this cooling tower repair job. It was the best for improving the operation of cooling system of TWH. Well done!”
I never took into account the fact that cooling towers could even be the cause for the closing of the hospital when it is not in good running condition. That statement will be a good reminder for those involved in hospital management and they will definitely find your article very helpful. If my advice will be sought with regards to a malfunctioning cooling tower, I will quickly suggest to give it proper care and never take that for granted and seek the help of those who can help them keep their cooling tower stable and functional as much as possible.
LikeLike
Thanks Renz
LikeLike